2018 Trail Construction Updates

New!  April 16, 2018:  We have confirmed that the Bid Letting for the Bridge project will be on May 4, 2018.  That means a contractor will be chosen that day.  We do not know the exact date, but based on the bid letting date, the trail will most likely be closed sometime during the week of June 4, 2018.  We will post a definite date when we have one!

TRAIL IS OPEN – TREE REMOVAL WORK IS COMPLETE.

TRAIL CLOSURE REMINDER: The Paint Creek Trail will be closed between Dutton and Silver Bell all day on Thursday, March 22, and for half the day on Friday, March 23. Tree removal contractors will be on site removing trees in preparation for our Paint Creek Trail Bridge 33.7 replacement, tentatively scheduled to start in June 2018. Please plan your visit on Thursday and Friday accordingly.

Trail Closure Update: The Paint Creek Trail will be OPEN today and tomorrow. The tree removal work scheduled for today has been postponed until Thursday, March 22 and Friday, March 23. We will post a reminder later in the week.

Trail Closure Notice: The trail is tentatively scheduled to be closed to thru traffic at Bridge 33.7 (between Dutton and Silverbell) on Monday, March 19, 2018 and possibly Tuesday, March 20, 2018. A tree service company will be on site removing 22 trees near the bridge, in preparation for the bridge replacement in June. Please plan your visit to the trail accordingly. We will post more information as it becomes available.

*2018 Paint Creek Trail Construction and Closure Alert*

Paint Creek Trail is scheduled for two major construction projects in 2018.

Bridge 33.7, which is located on the trail between Dutton and Silver Bell Roads, is scheduled to be replaced.  This $750,000 project, which is being funded by a $300,0000 Michigan Natural Resources Trust Fund Grant, a $300,000 Federal Transportation Alternatives Program grant, and a $150,000 cash match from Oakland Township Parks and Recreation, is scheduled to start in late Spring or early Summer 2018.  The Paint Creek Trail will be completely closed to thru traffic for 60-90 days.  Unfortunately, there is no detour.  You will be able to use the trail from Rochester Municipal Park to Dutton Road, or Silver Bell Road to Children’s Park in Lake Orion. The one mile section between Dutton Road and Silver Bell Road will be completely closed during the bridge replacement. Please plan your visit to the Paint Creek Trail accordingly.  After the bridge is replaced, the Paint Creek Trail is tentatively scheduled to be re-surfaced with crushed limestone, from Rochester to Lake Orion, with rolling closures.  At this time, bridge construction is tentatively planned to start around June 1, 2018 and both projects will tentatively be completed by September 30, 2018. This schedule is tentative, and subject to change.

You can get regular updates on the construction and trail closures the following ways:

  • Paint Creek Trail FaceBook Page: https://www.facebook.com/paintcreektrail/
  • Paint Creek Trail Twitter Page: https://twitter.com/paintcreektrail
  • Paint Creek Trail Website Page: http://paintcreektrail.org/wordpress/2018-trail-construction-updates
  • Email: manager@paintcreektrail.org
  • Phone: 248-651-9260